AEY 2023-24 General Rate Application
Transcript
November 27, 2023
November 28, 2023 - Revised for Time Zone correction
November 29, 2023
November 30, 2023
Hearing Undertakings
YUB - IPPs Written Questions to AEY, Nov. 29, 2023
AEY Hearing Undertakings - Cover Letter - Dec. 4, 2023
AEY Hearing Undertakings, Dec. 4, 2023
Undertaking 21 - Attachment 1
Application
ATCO Electric Yukon 2023-24 GRA, July 7, 2023
2023-24 GRA Regulatory Schedules
Section 01 - Attachment 1.2
Section 02 - Attachment 2.1
Section 02 - Attachment 2.2
Section 11 - Attachment 11.2
Business Cases 01-03
Business Cases 04-21
Business Cases 22-38
Business Cases 39-41
AEY Depreciation Parameter Information Letter, Sept 11, 2023
2023-24 GRA Updated Regulatory Schedules re Depreciation Study
Attachment 1 - 2022 Depreciation Study Report
Section 07 - Updated Depreciation
Section 07 - Updated Depreciation - blackline version
AEY Updates to 2023-24 General Rate Application, Oct. 30, 2023
ATCO Electric Yukon - Omissions & Updates - Blackline
ATCO Electric Yukon - Omissions & Updates - Clean
ATCO Electric Yukon - GRA Regulatory Schedules - Omissions & Updates - Blackline
ATCO Electric Yukon - GRA Regulatory Schedules - Omissions & Updates - Clean
AEY letter re Concentric Business Risk Report additional documents, Nov. 20, 2023
JPT-2 Risk Premium Comparison
JPT-3 Small Size Premium
Ministerial Direction
YUB letter to Minister re AEY 2023-24 GRA, July 12, 2023
Letter from Minister re AEY GRA, July 20, 2023
Board Orders
Board Order 2023-13 re AEY GRA proceeding, July 14, 2023
Board Order 2023-14 Erratum re AEY GRA proceeding interveners and distribution list, Aug. 11, 2023
Board Order 2023-15 re AEY GRA proceeding schedule, Aug. 17, 2023
Board Order 2023-18 re AEY GRA proceeding schedule, Aug. 29, 2023
Board Order 2023-22 re AEY GRA interim rates
Appendix A
Board Order 2023-24 re AEY IR Responses
Appendix A
Appendix B
Board Order 2024-01 re AEY 2023-2024 GRA proceeding decision, May 31, 2024
Appendix A
Board Order 2024-04 re AEY 2023-2024 GRA Complinance Filing Process, July 5, 2024
Board Order 2024-06 AEY 2023-2024 GRA Compliance Filing Decision
Appendix A
Attachment 1 Rider R
Attachment 2 Rider R1
Correspondence and Other Information
Distribution list for AEY GRA, Updated Nov. 8, 2023
AEY letter to YUB re process steps, July 17, 2023
YUB reply to AEY re proceeding schedule, July 18, 2023
Frank Bachmier letter re presenting at AEY GRA, Jul 27, 2023
YEC comments re AEY interim rate request, Aug 4, 2023
Maissan comments re AEY interim rate request, Aug 4, 2023
Yukon NDP Caucus comments re AEY interim rate request, Aug 4, 2023
AEY Response to Intervener Submissions, Aug. 10, 2023
AEY Letter re Process Schedule & Procedural Matters, Aug. 14, 2023
Nathaniel Yee response re Process Schedule, August 14, 2023
John Maissan response re process schedule, Aug 16, 2023
UCG response re process schedule, Aug 16, 2023
Yukon NDP Caucus response re process schedule, Aug. 17, 2023
AEY response re Process Schedule, Aug 18, 2023
YUB letter to NDP Caucus re AEY IRs, Oct. 4, 2023
UCG motion re further IR Responses, Oct. 5, 2023
Nathaniel Yee motion re further IR responses, Oct 5, 2023
YUB letter to AEY GRA Parties re Yee & UCG Motions, Oct. 6, 2023
AEY response to Yee and UCG motions, Oct. 10, 2023
Appendix A
Appendix B
UCG reply to AEY comments re further IR Responses, Oct. 12, 2023
Nathaniel Yee reply to AEY comments re further IR Responses, Oct. 12, 2023
AEY request for IR response extension, Oct. 20, 2023
YUB letter to AEY re IR response deadline extension, Oct. 20, 2023
YUB letter to Parties regarding proceeding direction, Nov. 7, 2023
Comments
Letter from Frank Bachmier re presenting at AEY GRA, July 27, 2023
CFIB letter re AEY Rate Hike, July 31, 2023
Interveners
Yukon Conservation Society application for intervener stauts, July 21, 2023
YEC application for intervener status, July 31, 2023
John Maissan request for intervener status, July 31, 2023
Florian Boulais request for intervener status, Aug 2, 2023
Nathaniel Yee request for intervener status, Aug 3. 2023
UCG request for intervener status, Aug 4, 2023
Yukon NDP Caucus request for intervener status, Aug. 4, 2023
Information Requests
YUB IRs, Sept 6, 2023
UCG IRs, Sept. 6, 2023
John Maissan IRs, Sept. 6, 2023
Nathaniel Yee IRs, Sept. 6, 2023
Yukon NDP Caucus IRs, Sept. 6, 2023
Florian Boulais IRs, Sept. 6, 2023
YUB Round 2 IRs, Oct. 10, 2023
John Maissan Round 2 IRs, Oct. 10, 2023
UCG Round 2 IRs, Oct. 10, 2023
Responses to Information Requests
AEY Consolidated IR Responses, Sept. 28, 2023
AEY IR Responses to YUB - Part 1 of 2
AEY IR Responses to YUB - Part 2 of 2
001(f) Attachment
001(h) Attachment
002(b) Attachment
045(a) Attachment
046(a) Attachment
067(f) Attachment
070(b) Attachment
AEY IR Responses to YUB-65 and YUB-66
AEY IR Responses to UCG Part 1 of 9, Sept. 28, 2023
003(d) Attachment
007(a) Attachment
025 Attachment
026(a) Attachment
027(a) Attachment
031(a) Attachment
050(b) Attachment
050(f) Attachment
053(e) Attachment
054(d) Attachment
055(1) Attachment
101(a) Attachment
AEY IR Responses to UCG Part 2 of 9, Sept. 28, 2023
AEY IR Responses to UCG Part 3 of 9, Sept. 28, 2023
AEY IR Responses to UCG Part 4 of 9, Sept. 28, 2023
AEY IR Responses to UCG Part 5 of 9, Sept. 28, 2023
AEY IR Responses to UCG Part 6 of 9, Sept. 28, 2023
AEY IR Responses to UCG Part 7 of 9, Sept. 28, 2023
AEY IR Responses to UCG Part 8 of 9, Sept. 28, 2023
AEY IR Responses to UCG Part 9 of 9, Sept. 28, 2023
AEY IR Responses to John Maissan, Sept. 28, 2023
004(b) Attachment
025(a) Attachment
AEY IR Responses to Nathaniel Yee, Sept. 28, 2023
AEY IR Responses to Yukon NDP, Sept. 28, 2023
002(a) Attachment
AEY IR Responses to Florian Boulais, Sept. 28, 2023
AEY Round 2 IR Responses - Cover Letter, Oct. 24, 2023
AEY Round 2 IR Responses to YUB IRs, Oct. 24, 2023
001(e) Attachment
001(h) Attachment
001(l) Attachment
003(c) Attachment
AEY Round 2 IR Responses to Maissan IRs, Oct. 24, 2023
005(a) Attachment
AEY Round 2 IR Responses to UCG IRs, Oct. 24, 2023
002(a) Attachment
004(a-b) Attachment
AEY Response to Motions and YUB Directions - Oct. 27, 2023
Direction 3 - Consolidated Reference Documents 1 to 20
Direction 3 - Reference Documents 1 to 4
Direction 3 - Reference Documents 5 to 9
Direction 3 - Reference Documents 10 to 16
Direction 3 - Reference Documents 17 to 20
Direction 7 Attachment 1 - Schedule 9.2 Update - Blackline
Direction 7 Attachment 1 - Schedule 9.2 Update - Clean
Final Arguments
YEC Final Argument Dec. 13. 2023
AEY Letter enclosing Final Argument and Book of Authorities Dec. 13, 2023
AEY 2023-24 GRA Final Argument of AEY
Book of Authorities to the Final Argument
Nathaniel Yee Final Argument Dec. 13, 2023
Yukon NDP Caucus Final Argument Dec. 13, 2023
UCG Final Argument Dec. 13, 2023
Florian Boulais Information Requests Final Argument Dec. 13, 2023
John Maissan Final Argument, Dec. 13, 2023
Reply Arguments
John Maissan Reply Argument, Dec. 18, 2023
AEY Reply Argument, Dec. 20, 2023
Book of Authorities
Nathaniel Yee Reply Argument, Dec. 20, 2023
UCG Reply Argument, Dec. 20, 2023
Compliance Filing
AEY 2023-2024 GRA Compliance Filing, June 28, 2024 (includes all attachments)
Attachment 1
Attachment 4
Attachment 5
Attachment 6
Cost Claims Applications
Nathaniel Yee AEY 2023-2024 GRA Cost Claim Submission, June 12, 2024
AEY 2023-2024 Cost Claim Application, June 28, 2024
AEY 2023-2024 Cost Claim Excel File
AEY Submission of 2023-2024 GRA Cost Claim Affidavit, July 2, 2024
UCG AEY 2023-2024 GRA Cost Claim Application, June 29, 2024
UCG Cost Form1
UCG Cost Form 2
UCG Cost Form 3
UCG Cost Form 4
UCG Comments on AEY 2023-2024 GRA Cost Claim, July 12, 2024