Carmacks-Stewart Transmission Project (CSTP) - Part 3 Review
- Ministerial Direction
- Application for CSTP Part 3 Review
- Board Orders and Direction from the Board
- Correspondence
- Exhibits
- Intervenors and Observers
- Public Hearing
- Board Report to Minister of Justice
- Cost Applications
Ministerial Direction
-
Ministerial direction re CSTP Part 3 Review and Hearing - April 2, 2007 [1 MB
]
Application for CSTP Part 3 Review
-
Energy Certificate Application - April 2, 2007 [1 MB
]
Board Orders and Direction from the Board
-
YUB letter re PPA and Part 3 Review and Hearing - April 3, 2007 [28 KB
]
-
Board Order 2007-4 re Carmacks-Stewart Transmission Project and Part 3 Review - April 4, 2007 [254 KB
]
-
YUB letter re Intervenor and Observer Status - April 16, 2007 [76 KB
]
-
Board Order 2007-08 for CSTP Cost Awards [ 564 KB
]
Correspondence
-
YUB letter re YUB membership - April 13, 2007 [54 KB
]
Exhibits
Click here to view Exhibits page
Intervenors and Observers
Intervenors Yukon Electrical Company Ltd. Utilities Consumers’ Group Yukon Conservation Society Peter Percival Yukon Sustainable Energy Association
Observers John Maissan Gary McRobb Val Mather, Yukon Department of Energy, Mines and Resources Lawrie Crawford Paul Kishchuk
Public Hearing
-
Part 3 Review May 15, 2007 a.m. [411 KB
]
-
Part 3 Review May 15, 2007 p.m. [38 KB
]
-
Part 3 Review May 16, 2007 a.m. [298 KB
]
Board Report to Minister of Justice
-
YUB Report to Minister of Justice re CSTP Part 3 Review - May 31, 2007 [1.7 MB
]
Cost Applications
-
UCG claim for cost award - letter dated June 15, 2007 [33 KB
]
-
UCG claim for cost award - PIAC breakdown [81 KB
]
-
UCG claim for cost award - PIAC spreadsheet [64 KB
]
-
UCG clarification to the Board re cost award dated June 20,2007 [14 KB
]
-
Percival claim for cost award dated June 22, 2007 [332 KB
]
-
YCS claim for cost award dated July 3, 2007 [25 KB
]
-
YCS claim for cost award - expenses [20 KB
]
-
YECL claim for cost award dated June 29, 2007 [225 KB
]
-
YEC claim for cost award dated July 3, 2007 [185 KB
]
-
YEC comments re Intervenor cost applications, dated July 17, 2007 [122 KB
]
-
Board request to Peter Percival for clarification on cost claim, dated July 18, 2007 [151 KB
]
-
Board request to YEC for cost breakdown, dated July 19, 2007 [49 KB
]
-
Percival reply to Board request for clarification of cost claim, dated July 30, 2007 [164 KB
]
-
YEC reply to Board request for cost breakdown, dated July 31, 2007 [85 KB
]