YEC Tlingit Homeland Energy EPA

Transcripts

July 19, 2022 Transcript
July 20, 2022 Transcript

 

Application
 

YEC-THELP EPA Application cover letter, Jan. 20, 2022

YEC-THELP EPA Application January 2022

YEC presentation: Public Workshop - Buying Renewable Electricity from Atlin, Feb. 11, 2022

YEC Amended EPA cover letter, Apr. 21, 2022
YEC Amended EPA submission, April 2022
YEC Amended EPA submission - Blackline version, April 2022

YEC-THELP EPA update to conditions precedent, June 10, 2022

 

Ministerial Direction

Minister referral of YEC-THELP EPA, May 18, 2021


Board Orders and Correspondence

Board Order 2022-01 re YEC-THELP EPA proceeding, Feb. 1, 2022
Board Order 2022-02 re YEC-THELP EPA proceeding interveners, Feb. 17, 2022
Board Order 2022-05 re YEC-THELP EPA proceeding, Apr. 28, 2022
Board Order 2022-08 re UCG motion re YEC-THELP EPA proceeding, July 12, 2022 
   Appendix A
Board Order 2023-06 re YEC THELP EPA proceeding cost awards
   Appendix A
Board order 2023-06 re YEC THELP EPA Proceeding Cost Awards - Erratum
    Appendix A - Erratum

John Maissan Motion re further IR responses, Mar. 15, 2022
Nathaniel Yee Motion re further IR responses, Mar. 16, 2022

YUB letter to YEC & Parties re YEC-THELP EPA proceeding, Apr. 14,  2022
UCG Motion re postponing hearing, July 2, 2022
YUB letter to YEC & UCG re UCG motion, July 5 2022
YEC reply re UCG motion to postpone hearing, July 6, 2022
UCG Reply to YEC response re motion re postponing hearing, July 8, 2022
YUB letter re proess protocol re THELP hearing, July 12, 2022
YUB letter to YEC & UCG re UCG Motion, July 5, 2022
YEC letter re Witness Panel, July 14. 2022
YUB letter to Minister re THELP EPA, Oct 18, 2022
YUB report re YEC THELP EPA, Oct 18, 2022

Interveners

AEY application for intervener status, Feb 14, 2022
City of Whitehorse application for intervener status, Feb 14, 2022
UCG application for intervener status, Feb 14, 2022
John Maissan application for intervener status, Feb 14, 2022
Nathaniel Yee application for intervener status, Feb 14, 2022

Information Requests

YUB IRs, Feb. 24, 2022
City of Whitehorse IRs, Feb. 24, 2022
UCG IRs, Feb. 24, 2022
John Maissan IRs, Feb. 24, 2022
Nathaniel Yee IRs, Feb. 24, 2022

YUB Round 2 IRs re YEC-THELP EPA, June 6, 2022
John Maissan Round 2 IRs re YEC THELP EPA, June 6, 2022
 
UCG amended IRs, June 5, 2022

Responses to Information Requests

YEC cover letter to IR responses, Mar. 9 2022
YEC IR reponse to YUB, Mar. 9, 2022
YEC IR reponse to CoW, Mar. 9, 2022
YEC IR reponse to UCG, Mar. 9, 2022
YEC IR reponse to John Maissan, Mar. 9, 2022
YEC IR reponse to Nathaniel Yee, Mar. 9, 2022

YEC consolidated IR responses, Mar. 9, 2022

YEC IR response to John Maissan - Revised, Part 1, Mar. 17, 2022
YEC IR response to John Maissan - Revised, Part 2, Mar. 17, 2022
YEC IR response to Nathaniel Yee - Revised, Mar. 17, 2022

YEC amended consolidated Round 1 IR responses, Apr. 20, 2022
YEC amended consolidated Round 1 IR responses with tracked changes, Apr. 20, 2022

YEC consolidated Round 2 IR responses, June 27, 2022

Undertakings

YEC Undertaking #6 
    Undertaking #6 - Attachment 1
YEC Undertaking #7

Final Arguments

YEC Final Argument re THELP EPA, July 28, 2022
    YEC Correction re Final Argument, Aug 2, 2022
UCG Final Argument re THELP EPA, July 25, 2022
Maissan Final Argument re THELP EPA, July 28, 2022
NY Final Argument re THELP EPA, Jul 28, 2022

Reply Argument

Yukon Energy Corporation Reply Argument, August 4, 2022
UCG Reply Argument, Aug 4, 2022
Nathaniel Yee Reply Argument, Aug 4, 2022

Cost Applications

YEC cost claim, Nov. 17, 2022
Nathaniel Yee cost claim, Nov. 15, 2022