YEC Battery Energy Storage System (BESS) Project proceeding


Registration for virtual hearing
via Zoom

Webinar Registration - Zoom

Transcripts

May 4, 2021 Transcript
May 5, 2021 Transcript
May 6, 2021 Transcript

Application

YEC BESS Application, Jan 2021 
YEC Opening Statement - BESS Project review, April 30, 2021

Ministerial Direction

Minister referral of YEC BESS Project, Feb 2, 2021
YEC BESS Project Terms of Reference, Feb 2, 2021
YUB letter to Minister re BESS Project timelines, Mar 10, 2021
Minister response re BESS Project timelines, Apr 16, 2021

Board Orders and Correspondence

Transmittal letter to Minister re BESS Project report, Jun 30, 2021
YUB report re YEC BESS Project, Jun 30, 2021

Board Order 2021-03 re BESS Project proceeding
YUB Notice of Application and Hearing YEC BESS Project
Board Order 2021-05 re BESS Project proceeding interveners
Board Order 2021-06 re YEC BESS Project proceeding 
Board Order 2021-13 re YEC BESS Project proceeding cost awards, Sept. 26, 2021
     Board Order 2021-13 - erratum, Oct. 6, 2021

Distribution list for BESS Project 
AEY letter re BESS Project IRs, Mar 19, 2021
YUB letter re YEC BESS Project virtual hearing process, Apr 27, 2021
UCG Aid to Cross-Examination, May 3, 2021

Interveners

YCS application for intervener status, Feb 25, 2021
UCG application for intervener status, Feb 28, 2021
AEY application for intervener status, Mar 1, 2021
John Maissan application for intervener status, Mar 1, 2021

Information Requests

YUB IRs re BESS Project, Mar 19, 2021
YCS IRs re BESS Project, Mar 19, 2021
UCG IRs re BESS Project, Mar 19, 2021
John Maissan IRs re BESS Project, Mar 19, 2021

Responses to Information Requests

YEC cover letter re BESS Project IR responses, Apr 1, 2021
YEC response to YUB IRs, Apr 1, 2021
YEC response to YCS IRs, Apr 1, 2021
YEC response to UCG IRs, Apr 1, 2021
    YEC Attachment to UCG-YEC-1-10(a), April 1, 2021
YEC response to Maissan IRs, Apr 1, 2021

YEC BESS Project Consolidated IR Responses, Apr 1, 2021
    YEC Attachment to UCG-YEC-1-10(a), April 1, 2021

Undertakings

YEC Undertaking #6
YEC Undertaking #7
YEC Undertaking #8
YEC Undertaking #9
YEC Undertaking #10

Final Arguments

YEC Final Argument re YEC BESS Project, dated May 13, 2021
UCG Final Argument and Cover Letter re YEC BESS Project, May 13, 2021
YCS Final Argument re YEC BESS Project, dated May 13, 2021
Maissan Final Argument regarding YEC BESS project, May 13, 2021

Cost Applications

UCG cost claim and cover letter, July 16, 2021
YEC BESS Project - UCG Affidavit
YEC cost claim, July 30, 2021

UCG comments re YEC BESS costs, Aug 5, 2021