Exhibits

Exhibits List

Exhibits List - Combined
 

A Series - Yukon Utilities Board

B Series - Applicant (YEC)

C Series - Intervenors

     C1 - ATCO Electric Yukon (AEY)

     C2 - Utilities Consumers’ Group (UCG)

     C3 - Yukon Conservation Society (YCS)

     C4 - John Maissan


A Series - Yukon Utilities Board

A-1 Minister referral of YEC BESS Project, Feb 2, 2021

A-2 YEC BESS Project Terms of Reference, Feb 2, 2021

A-3 Board Order 2021-03 re BESS Project proceeding, Feb 18, 2021

A-4 YUB Notice of Application and Hearing YEC BESS Project, Feb 23, 2021

A-5 Board Order 2021-05 re BESS Project proceeding interveners, Mar 5, 2021

A-6 YUB letter to Minister re BESS Project timelines, Mar 10, 2021

A-7 YUB IRs re BESS Project, Mar 19, 2021

A-8 Minister response re BESS Project timelines, Apr 16, 2021

A-9 Board Order 2021-06 re YEC BESS Project proceeding, April 16, 2021

A-10 YUB letter re YEC BESS Project virtual hearing process, Apr 27, 2021
 

B Series - Applicant (YEC)

B-1 YEC BESS Application, Jan 2021

B-2 YEC cover letter re BESS Project IR responses, Apr 1, 2021

B-3 YEC BESS Project consolidated IR responses, Apr 1, 2021

B-4 YEC Attachment to UCG-YEC-1-10(a)

B-5 YEC Opening Statement, May 4, 2021

B-6 YEC Undertaking #1, May 5, 2021

B-7 YEC Undertaking #2, May 5, 2021

B-8 YEC Undertaking #3, May 5, 2021

B-9 YEC Undertaking #4, May 5, 2021

B-10 YEC Undertaking #5, May 6, 2021

C Series - Intervenors

C1-1 AEY application for intervener status, Mar 1, 2021

C1-2 AEY letter re BESS Project IRs, Mar 19, 2021
 

C2-1 UCG application for intervener status, Feb 28, 2021

C2-2 UCG IRs re BESS Project, Mar 19, 2021

C2-3 UCG Aid to Cross-Examination, May 3, 2021
 

C3-1 YCS application for intervener status, Feb 25, 2021

C3-2 YCS IRs re BESS Project, Mar 19, 2021
 

C4-1 John Maissan application for intervener status, Mar 1, 2021

C4-2 John Maissan IRs re BESS Project, Mar 19, 2021