Whitehorse Condominium Corporation 275
Timeline of Complaint and Documents
February 14, 2022 - Complaint from Benoit Charland and Meghan McKenna on behalf of members of Whitehorse Condominium Corporation 275 (WCC 275)
Appendix B
Appendix C
Appendix D
March 11, 2022 - Joint response to Complaint from AEY and YEC
March 16, 2022 - Letter from Board to WCC 275 advising of right to reply to response from AEY and YEC
March 31, 2022 - Reply Submission from WCC 275
May 29, 2023 - WCC 275 and AEY did not take issue with the Board members past involvement referred to in May 19, 2023 Letter
E-mail from WCC 275
Letter from AEY
June 20, 2023 - Board Information Requests (IRs) to WCC 275 and AEY, Round 1
July 5, 2023 - AEY - Responses to Board IRs Round 1
AEY-YUB-1-005 Attachment 1
AEY-YUB-1-006 Attachment 1
July 5, 2023 - WCC275 Responses to Board IRs Round 1
September 5, 2023 - Board IRs Round 2 to WCC 275 and AEY
October 6, 2023 - AEY Response to Board IRs Round 2
AEY-YUB-2-006(a) Attachment 1
October 6, 2023 - WCC 275 Response to Board IRs Round 2
October 2023 - The Board votes and the majority decision is to not approve the settlement agreement. Three Board members work on the majority decision.
December 8, 2023 - The majority members of Board finalize the decision on the outcome of the complaint. Two members decide to write a minority decision to be included in the Board Order.
February 1, 2024 - E-mail from Max Fraser about anticipated timeline for Board decision on Complaint
February 13, 2024 - Letter from the Board in Response to Max Fraser's e-mail
May 1, 2023 - One Board member’s position ends